Qatar's first new North Field East LNG train is not producing by mid-2027
The test By 30 Jun 2027, no LNG has been produced from the first North Field East train, as QatarEnergy states or two independent sources report; the event is judged on that date.
Not under way · Confidence: medium · Reviewed 3 Nov 2026 · Scores from 1 to 10
This page answers: What could happen, how it is scored, and who is exposed?
Using this page
- Read the two scores: Likelihood and Impact are kept apart.
- Check what is happening, each fact with its source.
- Use the calendar for the dates to watch.
Follow this riskSign in to follow; one weekly email if you ask for it.
Impact is the average of the four parts, rounded, plus one point when Canada is directly hit on two or more channels, up to 10.
Two separate scales from 1 to 10. Strature never multiplies or merges them.
What changed
Dated, newest first
- Two people aware of the plans (Reuters): first train ready to start operation in November; LNG output expected in the first quarter of 2027; QatarEnergy did not comment [6]
- Reuters: QatarEnergy expects the first North Field East train to start production in the first half of 2027, more trains in 2027 depending on the strait; chief executive: equipment cannot reach Qatar; North Field South in 2028 [2]
Why it matters
North Field East is the first phase of Qatar's plan to lift LNG capacity from 77 to 126 Mtpa; in May 2025 QatarEnergy said it would start in mid-2026. After the war began, the first train moved to the first half of 2027, and expansion equipment still could not reach Qatar through the Strait of Hormuz. Two people told Reuters in October that the train would be ready in November, with LNG output in the first quarter of 2027.
Why Likelihood 4 A not-by-a-date event, judged on 30 Jun 2027. First LNG on time is the base case of the company and of the October Reuters report, which gives 4-5. Pushes: equipment blocked by the strait; one slip already, from mid-2026.
Why Impact 4 Threshold case the first train starts some months after 30 Jun 2027.
The other facts on file (4)
- QatarEnergy: North Field East to begin production in mid-2026; capacity to 126 Mtpa by 2027 from 77 Mtpa [1] (21 May 2025)
- QatarEnergy chief executive to Reuters: two existing LNG trains, 17% of export capacity, damaged in March and out for three to five years [3] (19 Mar 2026)
- Fitch: the war has had only a small impact on the first phase; substantial capacity rise from 2027 depending on the strait; return to budget surplus in 2027 [4] (4 Sep 2026)
- FIBA secretary general: Qatar not affected by the hostilities since 1 April [5] (5 Jun 2026)
Where it sits
How it spreads
The strait is the interchange. Each line is a good the shock travels by; each stop is a country on it. A figure at a stop is that country's share of its imports of that good that pass through Hormuz. The producers feed it first; their figure is the share of their exports that passes the strait. Dashed lines are the pipelines round it. Every figure is listed below with its source. Not to scale.
Every figure on the diagram, with its source
- Iran 100.0% Gulf producer Strature calculation from IEA (Kpler data) · 2025 · FH-1374
- Kuwait 100.0% Gulf producer Strature calculation from IEA (Kpler data) · 2025 · FH-1214
- Qatar (LNG) 93.0% Gulf producer IEA (Kpler data) · 2025 · FH-1303
- Iraq 89.6% Gulf producer Strature calculation from Shafaq News · 2025 · FH-1333
- Saudi Arabia 82.0% Gulf producer Strature calculation from US Energy Information Administration · Q2 2024 · FH-1527
- United Arab Emirates 63.0% Gulf producer Strature calculation from IEA (Kpler data) · 2025 · FH-1253
- Vietnam 80.0% Crude oil Strature calculation from MarketScreener · 2025 · T2A-0046
- South Korea 68.0% Crude oil EIA (Vortexa data) · 1Q25 · FH-0750
- Japan 67.7% Crude oil Strature calculation from US Energy Information Administration · 2025-Q1 / 2025 · CL-0003
- Taiwan 62.0% Crude oil PTS News (Taiwan) · 2025 · T2A-0004
- Bangladesh 50.0% Crude oil Strature calculation from Prothom Alo English · 2025-26 · T2M-0109
- China 46.6% Crude oil Strature calculation from US Energy Information Administration · 2025-Q1 / 2025 · CL-0001
- Pakistan 90.0% LNG Strature calculation from CSIS · 2025 · T2A-0077
- India 55.1% LNG Strature calculation from J.M. Baxi Marine Services · Apr 2025-Jan 2026 · FH-0786
- Taiwan 34.0% LNG PTS News (Taiwan) · 2025 · T2A-0013
- China 33.0% LNG US Energy Information Administration · 2025-H1 · FH-0098
- South Korea 20.0% LNG Strature calculation from Zawya · 2025 · FH-0127
- European Union 8.08% LNG European Commission · 2025 · FH-0972
- UAE Habshan-Fujairah crude line 1.8 mb/d bypass pipeline US Energy Information Administration · 2026 · pipelines_v1:are-adcop
- Iraq-Türkiye Kirkuk-Ceyhan crude line 1.52 mb/d bypass pipeline BOTAŞ · 2026 · pipelines_v1:irq-tur-kirkuk-ceyhan
- Saudi East-West crude line 7.0 mb/d bypass pipeline International Energy Agency · 2025 · pipelines_v1:sau-east-west
By 30 Jun 2027, no LNG has been produced from the first North Field East train, as QatarEnergy states or two independent sources report; the event is judged on that date.
Not under wayGoods 1
Sectors 1
- Energy and pipelines
Straits 1
Countries 6
Who is exposed
Share of LNG imports through Hormuz
- Sectors
- Energy and pipelines
- Goods
- LNG
- Straits
- Strait of Hormuz
Three scenarios and their signposts
- S1
On time
The first train starts in the first half of 2027.
- S2
Strait slip
Equipment and carriers stay blocked and the start moves to late 2027.
- S3
War slip
Renewed strikes damage the site or halt work.
| Path | Signpost |
|---|---|
| S1 | Feed gas introduced at the first train |
| S2 | New guidance from QatarEnergy |
| S3 | New damage reported at Ras Laffan |
No probability is given for the three paths.
Dates to watch
The dates to watch
A dot is a day, a bar a month or a year; a hollow mark is tentative. The line marks today.
- 30 Jun 2027 End of the first half of 2027, QatarEnergy's start target [2] Tentative · Strature date
Sign in, with alerts on, for an email 7 days and 1 day before.
Connected in Strature
- LNG
- Strait of Hormuz
- Qatar
- European Union
- Japan
- South Korea
- China
- India
- The Strait of Hormuz shuts again Driven by: Equipment and carriers must cross the strait.
- A missile or drone damages Qatar's gas plants at Ras Laffan or Mesaieed again Shares a channel: The same site; new damage would delay both.
- A winter LNG crunch forces gas rationing in Europe, Japan or South Korea Drives: A later start keeps the market tight.
Sources
6 sources, numbered as the text cites them
- Qatar's North Field East gas expansion to begin output in mid-2026. The New Arab · 21 May 2025 · News · confidence medium · retrieved 3 Nov 2026
- QatarEnergy's LNG expansion faces delays from Hormuz crisis. Offshore Engineer (Reuters) · 21 Sep 2026 · News · confidence medium · retrieved 3 Nov 2026
- Iran attack wipes out 17% of Qatar's LNG capacity for up to five years. gCaptain (Reuters) · 19 Mar 2026 · News · confidence medium · retrieved 3 Nov 2026
- Fitch Affirms Qatar at 'AA'; Outlook Negative. Fitch Ratings (via Zawya) · 4 Sep 2026 · Industry · confidence high · retrieved 3 Nov 2026
- FIBA still planning for Basketball World Cup in Qatar in 2027 as scheduled. AP (via WTOP) · 5 Jun 2026 · News · confidence medium · retrieved 3 Nov 2026
- Launch of new Qatar LNG train moves to counter Iranian attack losses. Baird Maritime (Reuters) · 7 Oct 2026 · News · confidence medium · retrieved 3 Nov 2026
Reviewed 3 Nov 2026 · version 1 · last change: first review · All risks