World risk · Energy and resources

AI grid queue: two or more European grids ration new data-centre connections

The test Between 3 Nov 2026 and 3 Nov 2027, in two or more of Denmark, Great Britain and the Netherlands, the national energy regulator, transmission operator or government adopts a binding decision that stops new grid connection agreements for large loads, caps the capacity open to data centres or large loads, or sets a data-centre-specific fee, milestone or flexibility condition to obtain or keep a connection. Consultations and municipal rules do not count; a rule adopted before 3 Nov 2026 counts only if it is extended or tightened inside the window.

Not under way · Confidence: medium · Reviewed 3 Nov 2026 · Scores from 1 to 10

This page answers: What could happen, how it is scored, and who is exposed?

Using this page
  1. Read the two scores: Likelihood and Impact are kept apart.
  2. Check what is happening, each fact with its source.
  3. Use the calendar for the dates to watch.

Follow this riskSign in to follow; one weekly email if you ask for it.

Likelihood
6Elevated steady this month
Impact
5Elevated steady this month
Breadth5
Depth2
Duration7
Hard to substitute4
Canada pointNot added0

Impact is the average of the four parts, rounded, plus one point when Canada is directly hit on two or more channels, up to 10.

Two separate scales from 1 to 10. Strature never multiplies or merges them.

What changed

Dated, newest first

  1. Netherlands (undated government page): from 1 Jul 2026 only three groups keep priority for grid connections in congested areas (grid relief, national security, basic needs); data centres not named [5]
  2. Dansk Erhverv: the pause is lifted under a four-category priority model Parliament adopted in October; data centres are in category 4; Energinet judges full access for categories 3 and 4 difficult in the short term; first answers to them due later in November [8]
  3. Ingeniøren: Energinet close to reopening the grid after months of a total stop; Dansk Erhverv called the situation untenable [2]

Why it matters

Requests to connect data centres far exceed what national grids can carry. Denmark paused new connections in March 2026 and reopened with data centres last in the queue; Britain's regulator has proposed a data-centre fee; the Netherlands set a social priority order. Will two grids adopt new binding rules?

Why Likelihood 6 Pushes: Ofgem's decision is pending; Energinet expects to limit access for data centres. Brakes: Denmark's law predates the window; Ofgem sets no decision date; the Dutch limb is weak. No source treats two new binding rules as the base case, so 6, not 7.

The other facts on file (6)
  • Energinet stopped signing new grid connection agreements for three months, or until it had an overview, against about 60 GW of queued demand and a peak use of about 7 GW; data centres, batteries and Power-to-X named as drivers [1] (2 Mar 2026)
  • Ofgem consultation proposes a data-centre commitment fee and queue management milestones with penalties; closed, awaiting decision [3] (29 Jul 2026)
  • Ofgem: proposed commitment fee of GBP 237,500 to 712,500 per MW, refunded at energisation, forfeited if the project leaves the queue early [9] (29 Jul 2026)
  • techUK: fee applies to projects above 40 MW; 73 GW of data-centre applications in the queue [4] (29 Jul 2026)
  • Fingrid: data-centre connection agreements nearly 5 GW; consumption could rise nearly 40% if all were built [6] (18 Aug 2026)
  • IEA: data-centre electricity use expected to more than double by 2030 [7] (2025)

Where it sits

DENMARK11. AI grid queue: two or more European grids ration new data-centre connections: Elevated impact · possible (placed at the country)1 Grids ration data-centrepowerElevated impact · possibleGRIDS RATION DATA-CENTRE POWER0200 kmat 56°NMap data: Natural Earth (public domain).
DENMARK11. AI grid queue: two or more European grids ration new data-centre connections: Elevated impact · possible (placed at the country)1 Grids rationdata-centre powerGRIDS RATION DATA-CENTRE POWER0200 kmat 56°NMap data: Natural Earth (public domain).

How it spreads

Sample, no data on file. No cited flows by country on file for this risk.

If

Between 3 Nov 2026 and 3 Nov 2027, in two or more of Denmark, Great Britain and the Netherlands, the national energy regulator, transmission operator or government adopts a binding decision that stops new grid connection agreements for large loads, caps the capacity open to data centres or large loads, or sets a data-centre-specific fee, milestone or flexibility condition to obtain or keep a connection. Consultations and municipal rules do not count; a rule adopted before 3 Nov 2026 counts only if it is extended or tightened inside the window.

Not under way

Channels 4 on the card

  1. CanadaNo Canadian loss sourced.
  2. Data-centre sitingProjects without a connection move to grids with spare capacity or wait (Strature's view).
  3. Cost of a queue placeA British fee ties up £23.8m to £71.3m for a 100 MW project until energisation [4].
  4. ElectrificationRationing also slows batteries and Power-to-X [1][8].

Sectors 2

  • Technology
  • Energy and pipelines

Countries 3

Who is exposed

No figure on file: Denmark, United Kingdom, Netherlands.

Sectors
Technology, Energy and pipelines

Three scenarios and their signposts

  1. S1

    Two grids ration

    Ofgem confirms the fee; Energinet caps data-centre access.

  2. S2

    One grid only

    Denmark adds no new limits.

  3. S3

    Build, not ration

    New capacity eases the queues.

The signposts of each scenario
PathSignpost
S1Ofgem's decision
S2Energinet's category 4 answers
S3New large-load agreements

No probability is given for the three paths.

Dates to watch

Calendar

The dates to watch

A dot is a day, a bar a month or a year; a hollow mark is tentative. The line marks today.

  1. Nov 2026 Denmark: Energinet's first answers to category 3 and 4 applicants [8] Declared · Strature date
  2. Jan 2027 Netherlands: leftover reserved grid capacity released to the waiting list [5] Declared · Outside event
SourceStrature world-risk card; the dates cite the sources below.
Exhibit R-3 · WORLD · strature.net

The other side

Clearing speculative projects can speed real ones: Ofgem aims to remove non-viable projects from the queue [3]. Denmark's October law came before the window, so it counts only if tightened [8].

Connected in Strature

Sources

9 sources, numbered as the text cites them

  1. Energinet indfører midlertidig pause i nye nettilslutninger og sætter turbo på akutpakke. Energinet (Via Ritzau) · 2 Mar 2026 · Official · confidence high · retrieved 3 Nov 2026
  2. Efter måneder med totalt stop: Energinet er tæt på at åbne for elnettet igen. Ingeniøren · 20 Oct 2026 · News · confidence medium · retrieved 3 Nov 2026
  3. Proposed data centre connection reforms. Ofgem · 29 Jul 2026 · Official · confidence high · retrieved 3 Nov 2026
  4. Ofgem details proposals to remove speculation from the demand connections queue. techUK · 29 Jul 2026 · Industry · confidence medium · retrieved 3 Nov 2026
  5. Kabinet neemt maatregelen tegen vol elektriciteitsnet (netcongestie). Rijksoverheid · 2026 · Official · confidence medium · retrieved 3 Nov 2026
  6. Electricity consumption is set to increase sharply. Fingrid · 18 Aug 2026 · Official · confidence high · retrieved 3 Nov 2026
  7. Energy and AI: Executive summary. International Energy Agency · 2025 · International body · confidence high · retrieved 3 Nov 2026
  8. Pausen i nye nettilslutninger er ophævet: Se hvad det betyder for din virksomhed. Dansk Erhverv · 21 Oct 2026 · Industry · confidence medium · retrieved 3 Nov 2026
  9. Ofgem acts to free up grid capacity by tackling speculative data centre projects. Ofgem · 29 Jul 2026 · Official · confidence high · retrieved 3 Nov 2026

Reviewed 3 Nov 2026 · version 1 · last change: first review · All risks