Will the long-form definitive agreements of the Labrador hydro programme still be unsigned on 31 December 2026?
From C-006Sealed 1 Oct 2026Resolves by 31 Dec 2026Open
Our standing estimate
One forecast: the estimate that it happens, and its complement. Our estimate, scored when it resolves.
1
The Labrador hydro programme misses its own date for binding agreements
60% · likely · confidence not registered
F-0171 · Open
It does not happen
40%
The situation when it was sealed (1 Oct 2026). The parties to the Labrador hydro programme set 31 December 2026 as their own date to sign long-form definitive agreements.
How it moved
Each point is a sealed register row. There is one sealed estimate for each outcome so far: a new point is added only when we register a new estimate, and the old one stays listed and scored.
The vertical line is 31 Oct 2026. Numbers match the outcomes above.
Every sealed estimate for this question: outcome number, register row, date sealed, estimate, status
No.
Row
Sealed
Estimate
Status
1
F-0171
1 Oct 2026
60%
Open
Reassessments
No reassessment yet.
Signposts
What the brief says would move the view, quoted from it.
No signpost is published for this question yet.
Why it matters, by category
Energy and resources
The test is whether the parties keep their own timetable, judged on their own releases.
Countries it touches
The countries our register links to these forecasts, most often linked first.
Each probability is our estimate, scored when it resolves. Forecasts are general research on public events and policy; they are not investment, legal or tax advice.